Bayliss Boatworks construction update: Bayliss 75'

by Bayliss Boatworks 7 Aug 16:02 UTC

The last month was an eventful one for Bayliss 75' as well. After installing three layers of bottom planking, followed by three layers of side planking, our Hull Carpentry Crew celebrated placing the final plank on the hull with our ceremonial "whiskey plank."

With this benchmark under their belts, the crew turned their attention to fabricating and installing the bow thruster tube and transducer box. In early August, the planking screws will be removed and filled, then cut and sanded smooth, before turning the boat over to our Paint Crew for glassing and fairing.

On the cabin, the flybridge was set into place and the two components were faired together seamlessly. The hand rail was fabricated, faired, and is currently undergoing rounds of sanding. The center console was also positioned into place on the flybridge, where it will transition into final primer with the rest of the cabin.

Read more about Bayliss 75' here.

Related Articles

Bayliss 67' Overtime construction update
The cabin has transitioned from glass, to epoxy, to fairing In October, the cabin for Overtime (Bayliss 67') transitioned from glass, to epoxy, to fairing. As the cabin progressed through rounds of sanding, work also began on the flybridge. Posted on 5 Nov
Bayliss 75' construction update
Interior insulated, planked, and glassed inside Hull Shop After her flip right side up in September, the interior of Bayliss 75' was insulated, planked, and glassed inside our Hull Shop. Next, her three main bulkheads were fabricated, installed, and securely glassed into place. Posted on 4 Nov
Bayliss 72' Old Reliable construction update
Getting to the stage in the build process where things seem to develop at a rapid pace Old Reliable (Bayliss 72') is getting to the stage in the build process where things seem to develop at a rapid pace. In late October, she transitioned to our make-ready bay where our Exterior Carpentry work continues within the cockpit. Posted on 3 Nov
Bayliss 62' Seven construction update
Getting close to her christening date! In October, our department supervisors gathered in the cockpit to depart on Seven's first sea trial. She performed beautifully, surpassing our expectations for speed, even before running gear finalizations. Posted on 2 Nov
Bayliss 75 construction update
The hull sides were glassed, coated in epoxy, faired, and primed September was a month of rapid change on the exterior of Bayliss 75'. With her engine vents installed, the hull sides were glassed, coated in epoxy, faired, and primed. Posted on 6 Oct
Bayliss 72' Old Reliable construction update
Color sanding on the hull sides and cabin is now under way On Old Reliable, the most striking change you'll notice is the bow deck. In September, the toe rail was installed before the entire deck was coated in primer. Posted on 4 Oct
Bayliss 62' Seven construction update
Seven's custom transom artwork was completed by Everett Nautical In late September, Seven emerged from the paint bay with the hull glistening in final paint, and the cabin wrapped for protection. The crane arrived and our crews assisted Palm Beach Towers with the seamless installation of the tower and hard top. Posted on 2 Oct
Bayliss 75 construction update
After prepping the hull, glassing began After celebrating Bayliss 75's "whiskey plank" in July, the planking screws were removed and filled with golf tees, then cut and sanded smooth. After prepping the hull, glassing began. Posted on 7 Sep
Bayliss 72' Old Reliable construction update
The bow deck on Old Reliable really took shape over the course of the last month The bow deck on Old Reliable (Bayliss 72') really took shape over the course of the last month. Once planking was completed, the bow deck was glassed, coated in ad tech, and faired. Posted on 5 Sep
Bayliss 62' Seven construction update
On the home stretch with the Paint & Fair Crew hard at work Seven (Bayliss 62') is in the home stretch! In late August, she moved into our paint bay where she received final paint. Our Paint & Fair Crew began their work with the application of a custom-blended shade of Imron "Cool Blue" on Seven's hull. Posted on 3 Sep