Please select your home edition
Edition
Sail-World Asia
Sail-World Australia
Sail-World Canada
Sail-World Europe
Sail-World New Zealand
Sail-World United Kingdom
Sail-World USA
YachtsandYachting.com
Cruising Northern Hemisphere
Cruising Southern Hemisphere
Marine Business Europe
Marine Business North America
Marine Business Oceania
Powerboat.World Europe
Powerboat.World North America
Powerboat.World Oceania
FishingBoating.World Australia
FishingBoating.World New Zealand
FishingBoating.World USA
FishingBoating.World Asia
FishingBoating.World Canada
FishingBoating.World Europe
FishingBoating.World United Kingdom
NZ Boating World
Show Menu
HOME
EDITORIAL
CATAMARANS
PARIS 2024
FAVOURITES
CLUBS
CLASSES
CALENDAR
FORUM
PHOTOS
VIDEOS
PARTNERS
CLASSIFIEDS
JOBS
SHOPPING
NEWSLETTERS
SUBMIT NEWS
CONTACT
STATS
Bayliss Boatworks new construction and boatyard updates
by Bayliss Boatworks 2 Jan 19:43 UTC
Happy New Year © Bayliss Boatworks
Boatyard Expansion February 2023
The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. 10 new boat slips and 15 additional workspaces were added on the hard top. Nearly 1,000 linear feet of bulkhead, a 12,000 gallon fuel tank, and 25 100 amp shore power pedestals were also part of the new addition. We are looking forward to utlizing the new space in the year ahead!
Top left: April - Installing Boat Slips ; Top right: August - Fuel Tank Install
Bottom: December - Boatyard Expansion
2023 Build Highlights
Aft Fuel Tank Install
Engine and Salon Deck Installs
Cabin Install
Mezzanine, Bridge, and Interior Buildout
Teak Deck, Border, and Coverboard Installs
Exterior Sanded and Primed
CLICK TO READ MORE ABOUT SEQUENTIS
2023 Build Highlights
Forward Fuel Tank Install
Engine, Generator, Salon Deck Installs
Aft Fuel Tank and Seakeeper 18 Installs
Cabin Install
Mezzanine, Interior, Flybridge Buildouts
Exterior Sanded and Primed
CLICK TO READ MORE ABOUT MAX BET
2023 Build Highlights
Hull Jig Assembled
Whiskey Plank
Bulkhead Install
Machine Tunnel and Engine Room Buildouts
Forward Fuel Tank Install
Engines, Generators, Seakeeper 18, and Salon Deck Installs
CLICK TO READ MORE ABOUT BAYLISS 75'
2023 Build Highlights
Project Start: August 2023
Hull Jig Assembled
Whiskey Plank
Hull Glassed and Sanded
CLICK TO READ MORE ABOUT BAYLISS 64'
Website
Facebook
Instagram
Copyright © 2024 Bayliss Boatworks All rights reserved.
www.baylissboatworks.com
Related Articles
Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water!
Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop.
Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together!
Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation.
Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis
January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed.
Posted on 3 Feb
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along!
Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete.
Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis
Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer.
Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis
Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids.
Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled
This past month, we assembled the hull jig for our latest project: Bayliss 64'.
Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75'
The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun.
Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
June was a productive month for our exterior carpentry team
June was a productive month for our exterior carpentry team on the walkaround build.
Posted on 1 Jul 2023
Bayliss Boatworks new construction updates
Progress on Sequentis 60', Max Bet 64' and Bayliss 75'
All the pieces are coming together on the 60' walkaround. Last month on Sequentis, the cockpit structural decking was installed, and epoxy was applied to the interior walls.
Posted on 2 Jun 2023