Bayliss Boatworks new construction updates: Sequentis 60', Max Bet 64', Bayliss 75', Bayliss 64'

by Bayliss Boatworks 2 Oct 2023 21:43 UTC
Bayliss 60' Sequentis © Bayliss Boatworks

Bayliss 60' Sequentis

Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids.

In the lower accommodations, the salon and galley walls have been installed and our interior carpentry team has been busy mocking up cabinetry items. Next on Sequentis, our crew will be installing her cockpit deck.

Read more about Sequentis

Bayliss 64' Max Bet

Forward progress is taking place on Max Bet. Our paint team worked on sanding and applying primer to the hull, bow deck, and cabin sides, while our exterior carpentry crew recently installed the cockpit fishbox and began the mezzanine buildout.

The mechanical crew has been busy in the interior installing ductwork. Over in the cabinet shop, our interior construction crew has fabricated the master and VIP vanity uppers and lowers. We are looking forward to beginning Max Bet's flybridge buildout next.

Read more about Max Bet

Bayliss 75'

Bayliss 75' is now hitting her install milestones. Our hull carpentry team completed the buildout of the fuel tank surround, while our paint team completed painting the area.

The forward fuel tank was installed by our mechanical team, and our hull carpentry team was also able to install the machine tunnel and forward fuel tank decks.

Later this month, Bayliss 75' will have her two MTU 16V 2000M96L engines installed.

Read more about Bayliss 75'

Bayliss 64'

All the pieces are coming together on Bayliss 64'. With the hull jig in place, our hull carpentry team installed the hull stem, then laminated and sanded the sheer log. The stringers were also set in place, and the hull carpentry team has sanded and shaped them. The planking process on Bayliss 64' will begin next!

Read more about Bayliss 64'

Related Articles

Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled This past month, we assembled the hull jig for our latest project: Bayliss 64'. Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75' The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun. Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
June was a productive month for our exterior carpentry team June was a productive month for our exterior carpentry team on the walkaround build. Posted on 1 Jul 2023
Bayliss Boatworks new construction updates
Progress on Sequentis 60', Max Bet 64' and Bayliss 75' All the pieces are coming together on the 60' walkaround. Last month on Sequentis, the cockpit structural decking was installed, and epoxy was applied to the interior walls. Posted on 2 Jun 2023