Please select your home edition
Edition
Sail-World Asia
Sail-World Australia
Sail-World Canada
Sail-World Europe
Sail-World New Zealand
Sail-World United Kingdom
Sail-World USA
YachtsandYachting.com
Cruising Northern Hemisphere
Cruising Southern Hemisphere
Marine Business Europe
Marine Business North America
Marine Business Oceania
Powerboat.World Europe
Powerboat.World North America
Powerboat.World Oceania
FishingBoating.World Australia
FishingBoating.World New Zealand
FishingBoating.World USA
FishingBoating.World Asia
FishingBoating.World Canada
FishingBoating.World Europe
FishingBoating.World United Kingdom
NZ Boating World
Show Menu
HOME
EDITORIAL
CATAMARANS
PARIS 2024
FAVOURITES
CLUBS
CLASSES
CALENDAR
FORUM
PHOTOS
VIDEOS
PARTNERS
CLASSIFIEDS
JOBS
SHOPPING
NEWSLETTERS
SUBMIT NEWS
CONTACT
STATS
Bayliss Boatworks new construction updates
by Bayliss Boatworks 2 Dec 2023 21:04 UTC
Progress on
Sequentis
is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Our exterior carpentry team has moved on to installing the teak coverboards in the cockpit, and teak border and lids in the mezzanine.
CLICK TO READ MORE ABOUT SEQUENTIS
Our crew stayed busy on
Max Bet
last month. The exterior carpentry team has been working on the bridge buildout and finished glassing the structural deck in the cockpit. Down in the engine room, our mechanical and electrical crews installed the engine and generator switches, as well as the engine room breakers.
CLICK TO READ MORE ABOUT MAX BET
November was a big month of installs for
Bayliss 75'.
The custom sportfishing yacht was moved just outside of the hull shop to have her engine room components installed. Our mechanical team worked efficiently, and
Bayliss 75'
is now equipped with two MTU 16V 2000M96L engines, two 40 kW Kohler generators, and a Seakeeper 18. With the help of our exterior carpentry team, her salon deck was installed and
Bayliss 75'
was moved back into the hull shop.
CLICK TO READ MORE ABOUT BAYLISS 75'
With planking complete on
Bayliss 64'
, sanding is underway in the hull shop. The engine vents have been glassed, and our hull carpentry crew is gearing up to glass the hull bottom and install the spray rails.
CLICK TO READ MORE ABOUT BAYLISS 64'
Website
Facebook
Instagram
Copyright © 2023 Bayliss Boatworks All rights reserved.
www.baylissboatworks.com
Related Articles
Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water!
Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop.
Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together!
Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation.
Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis
January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed.
Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead
The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close.
Posted on 2 Jan
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis
Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer.
Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis
Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids.
Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled
This past month, we assembled the hull jig for our latest project: Bayliss 64'.
Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75'
The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun.
Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
June was a productive month for our exterior carpentry team
June was a productive month for our exterior carpentry team on the walkaround build.
Posted on 1 Jul 2023
Bayliss Boatworks new construction updates
Progress on Sequentis 60', Max Bet 64' and Bayliss 75'
All the pieces are coming together on the 60' walkaround. Last month on Sequentis, the cockpit structural decking was installed, and epoxy was applied to the interior walls.
Posted on 2 Jun 2023