Bayliss Boatworks new construction updates: Sequentis 60', Max Bet 64', Bayliss 75', Bayliss 64'

by Bayliss Boatworks 2 Apr 19:11 UTC
Bayliss 60' Sequentis © Bayliss Boatworks

Bayliss 60' Sequentis

Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop.

Our electrical department has been busy wiring the hardtop and is now working on the bridge and main panels.

Our interior carpentry crew made progress on installations in the lower accommodations, and they will begin installing cabinets in the galley next.

Read more about Sequentis here

Bayliss 64' Max Bet

Last month was productive for our guys on Max Bet. Our exterior carpentry and paint crews continued progress on the mezzanine and bridge buildouts. Awlfair and Superbuild were both applied and sanding is now in the works.

In the interior, finish is being applied to veneers, and cabinetry items are getting installed in the lower accommodations. Max Bet is gearing up for a trip over to our paint facility in May, with priming on the to-do list this month.

Read more about the Max Bet

Bayliss 75'

With the anchor locker fully painted and protected, our carpentry crew has shifted focus to Bayliss 75's interior. With glassing in the lower accommodations complete, our paint crew has applied epoxy to the interior walls and floors.

In the salon, glassing and livos installations are under way. Down in the engine room, battery chargers, breakers, and transformers are now installed. In anticipation of the mezzanine buildout, our exterior team will begin working on structural decking in the cockpit.

Read more about the Bayliss 75'

Bayliss 64'

Work is moving along on Bayliss 64'. Over in the hull shop, our team continued progress with the machine tunnel and engine room buildouts, recently installing the port and starboard battery boxes in the engine room.

Currently our crews are sanding and priming in the machine tunnel and installing the lifting strakes and bow thruster diverter to the hull.

Read more about the Bayliss 64'

Related Articles

Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids. Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled This past month, we assembled the hull jig for our latest project: Bayliss 64'. Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75' The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun. Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
June was a productive month for our exterior carpentry team June was a productive month for our exterior carpentry team on the walkaround build. Posted on 1 Jul 2023
Bayliss Boatworks new construction updates
Progress on Sequentis 60', Max Bet 64' and Bayliss 75' All the pieces are coming together on the 60' walkaround. Last month on Sequentis, the cockpit structural decking was installed, and epoxy was applied to the interior walls. Posted on 2 Jun 2023