Bayliss Boatworks new construction updates

by Bayliss Boatworks 1 Jul 2023 23:44 UTC
 
June was a productive month for our exterior carpentry team on the walkaround build. On the bow, the anchor locker hatch has been installed. Progress on the fish box buildout continues in the cockpit, and coverboards are being installed as well. In the lower accommodations on Sequentis, mockups are being set in place by our interior carpentry crew! 
CLICK TO READ MORE ABOUT SEQUENTIS
 
Steady progress is being made on the 64' Max Bet. The anchor locker buildout is progressing on the bow, and the hatch is being fabricated. Our exterior carpentry team has been busy glassing the salon and lazarrette, and our interior carpentry team is working on installing mockups throughout the lower accommodations. Next month, crews will focus on glassing the bow deck and beginning the cockpit deck buildout.  
CLICK TO READ MORE ABOUT MAX BET
 
Since her recent flip, our team has been working hard over in the hull shop. Our paint crew continues to fair and sand the hull on Bayliss 75', and our hull carpentry team recently installed the bulkheads for the engine room, pump room, and lazarette. The bow thruster tube was recently installed and the machine tunnel buildout is currently in the works.
 
CLICK TO READ MORE ABOUT BAYLISS 75'
 
 
 
Website
Website
Facebook
Facebook
Instagram
Instagram

Copyright © 2023 Bayliss Boatworks All rights reserved.
www.baylissboatworks.com 

Related Articles

Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids. Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled This past month, we assembled the hull jig for our latest project: Bayliss 64'. Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75' The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun. Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
Progress on Sequentis 60', Max Bet 64' and Bayliss 75' All the pieces are coming together on the 60' walkaround. Last month on Sequentis, the cockpit structural decking was installed, and epoxy was applied to the interior walls. Posted on 2 Jun 2023