Please select your home edition
Edition
Sail-World Asia
Sail-World Australia
Sail-World Canada
Sail-World Europe
Sail-World New Zealand
Sail-World United Kingdom
Sail-World USA
YachtsandYachting.com
Cruising Northern Hemisphere
Cruising Southern Hemisphere
Marine Business Europe
Marine Business North America
Marine Business Oceania
Powerboat.World Europe
Powerboat.World North America
Powerboat.World Oceania
FishingBoating.World Australia
FishingBoating.World New Zealand
FishingBoating.World USA
FishingBoating.World Asia
FishingBoating.World Canada
FishingBoating.World Europe
FishingBoating.World United Kingdom
NZ Boating World
Show Menu
HOME
EDITORIAL
CATAMARANS
PARIS 2024
FAVOURITES
CLUBS
CLASSES
CALENDAR
FORUM
PHOTOS
VIDEOS
PARTNERS
CLASSIFIEDS
JOBS
SHOPPING
NEWSLETTERS
SUBMIT NEWS
CONTACT
STATS
Bayliss Boatworks new construction updates
by Bayliss Boatworks 2 Sep 2023 19:38 UTC
This past month, we assembled the hull jig for our latest project:
Bayliss 64'
. Attention to detail is a key component of the culture at Bayliss Boatworks, and it is maintained throughout every stage of the build process.
Across 2.5 days, our CNC department meticulously cut the 401 parts that would make up the hull's jig. Organization was essential to ensure the jig assembly ran without error. The pieces were stacked in boxes based on the order they would be laid and were then transfered over to our hull shop. Our hull carpentry team pieced together the stations and had the jig standing to completion in a matter of hours.
The cabin for the 64' build began this past June, and our team will be working on installing the hull stringers next. Be on the lookout for more info on our latest build!
CLICK TO READ MORE ABOUT BAYLISS 64'
In August, our team continued to make progress in the bridge on
Sequentis
. Our exterior carpentry crew installed the bridge dash jig base, and now have the dash in fabrication. Piece by piece, the teak decking and border is getting installed on the walkaround. Below deck, our cabinetry department has taken in the mockups and are now fabricating and finishing cabinetry items.
CLICK TO READ MORE ABOUT SEQUENTIS
Our crews have been knocking out their tasks on
Max Bet
. On the exterior, our paint department is sanding the cabin and bow deck. With the cockpit structural decking installed, our exterior team has begun the buildout for the coverboards. In
Max Bet's
interior, galley mockups are in place and our mechanical team has been busy with air handler installation in the lower accommodations.
CLICK TO READ MORE ABOUT MAX BET
August was a productive month on
Bayliss 75
. With our paint department painting in the machine tunnel, our hull carpentry crew installed the engine room aisleway framing and support. The team also fabricated the battery boxes and is installing the generator shelf in the engine room. With the fuel tank surround nearing completion, we are looking forward to the installation of her fuel tank next!
CLICK TO READ MORE ABOUT BAYLISS 75'
Website
Facebook
Instagram
Copyright © 2023 Bayliss Boatworks All rights reserved.
www.baylissboatworks.com
Related Articles
Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water!
Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop.
Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together!
Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation.
Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis
January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed.
Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead
The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close.
Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along!
Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete.
Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis
Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer.
Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis
Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids.
Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75'
The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun.
Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
June was a productive month for our exterior carpentry team
June was a productive month for our exterior carpentry team on the walkaround build.
Posted on 1 Jul 2023
Bayliss Boatworks new construction updates
Progress on Sequentis 60', Max Bet 64' and Bayliss 75'
All the pieces are coming together on the 60' walkaround. Last month on Sequentis, the cockpit structural decking was installed, and epoxy was applied to the interior walls.
Posted on 2 Jun 2023