Bayliss Boatworks construction update: Salty Tiger - Bayliss 62'

by John Bayliss 7 Apr 2020 15:04 UTC

With Salty Tiger returned to the make-ready bay with her full paint complete, our interior carpentry crew wasted no time getting back onto the vessel to begin cabinetry installations.

Within the galley, lower cabinetry has been installed. Upper cabinetry installations within the galley also began at the month's end. The galley floor was patterned and fabrication of the cork floors is now under way inside our interior carpentry shop. Our electrical crew just completed AC and DC wire runs and panel installations.

Within the lower levels, the staterooms are steadily being outfitted with teak furniture. The master stateroom has received its bunk, nightstands, dresser and hanging locker.

The guest and crew staterooms have received their bunks, dressers and hanging lockers. Vanities and shower doors are now being installed within the heads and our mechanical crew has completed the shower and sink plumbing in each head.

In late March, the transom artwork was completed. Now our paint crew will apply nearly a dozen coats of clear coat to protect the transom.

Within the heavy metalworks shop, our crew is developing patterns for the rub rail which will be fabricated soon. Our mechanical crew is preparing to install the ice maker and watermaker inside the engine room companionway. Over the course of the next month, fabrication of everything from tackle room cabinets to the salon door will take place within our cabinetry shop.

Read more about Salty Tiger here...

Related Articles

Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids. Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled This past month, we assembled the hull jig for our latest project: Bayliss 64'. Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75' The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun. Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
June was a productive month for our exterior carpentry team June was a productive month for our exterior carpentry team on the walkaround build. Posted on 1 Jul 2023