Bayliss Boatworks construction update: Bayliss 62'
by John Bayliss 6 Mar 2020 14:10 UTC
Bayliss 62' construction © John Bayliss
In early February, Bayliss 62' moved into our paint bay where she received full paint, beginning with a custom shade of Salty Gray on the hull.
Her bow deck was coated in non-skid paint and her faux teak helm pod, toe rail and half round received clear coat. During her move to the paint bay, our crews took advantage of the outdoor space to install the shafts.
Her engine room door was installed at the end of February, bringing her exterior appearance one step closer to completion.
Now that Bayliss 62' has returned to the make ready bay, our interior carpentry crew can begin teak cabinetry installations within the lower levels, including hanging lockers and dressers. Mechanically, our crews are beginning on plumbing in the heads.
Read more about Bayliss 62' here