Bayliss Boatworks construction update: Blue View - Bayliss 78'

by John Bayliss 9 Jan 16:03 UTC
Blue View - Bayliss 78' © John Bayliss

With the upper mezzanine and cockpit bulkhead in final clear coat, cabinetry installations have continued within the interior of Blue View. Bed frames are installed, head shower doors have been hung, and the salon sofa build-out is underway. Salon valances are being fabricated within our interior carpentry department now and it won’t be long before the salon door is installed.

In early December, our mechanical crew installed ice makers and connected the main engine exhausts. They are now making final preparations in the pump room for Blue View's first sea trial in February, after which, she'll receive her bootstripe and bottom paint!

Read more about Blue View here.

Related Articles

Salty Tiger - Bayliss 62' construction update
Within the galley lower cabinetry has been installed With Salty Tiger returned to the make-ready bay with her full paint complete, our interior carpentry crew wasted no time getting back onto the vessel to begin cabinetry installations. Posted on 7 Apr
Old Reliable - Bayliss 72' construction update
The machine tunnel is now completely in primer In late March, the forward fuel tank was installed, allowing our hull carpentry crew to complete the surrounding chases and prepare for the installation of the lower sole. Posted on 5 Apr
Seven - Bayliss 62' construction update
Over the course of March, the bow deck was planked and glassed With Seven's aft fuel tank, gyro and cabin installations complete, our exterior carpentry crew turned their focus to planking the bow deck and developing the flybridge arrangement. Posted on 3 Apr
Blue View - Bayliss 78' construction update
The month of March made things real for Blue View At the month's end, Blue View's transom artwork (protected by nearly a dozen coats of clear coat), bootstripe, and bottom paint were unveiled. Posted on 2 Apr
Blue View - Bayliss 78' construction update
The interior of Blue View progressed in leaps and bounds over the course of February The galley floor is now complete, padded panel installations are under way within the lower levels, and granite countertops have just been installed within the galley and lower levels. Posted on 8 Mar
Bayliss 62' construction update
Bayliss 62' moved into paint bay where she received full paint In early February, Bayliss 62' moved into our paint bay where she received full paint, beginning with a custom shade of Salty Gray on the hull. Posted on 6 Mar
Bayliss 72' construction update
The water tank and fuel tank surround are now in final epoxy coat With hull interior build out under way, Bayliss 72' is shaping up. Once all of her main bulkheads were glassed in, our hull carpentry crew turned their focus to building out the machine tunnel, water tank and fuel tank surround. Posted on 4 Mar
Bayliss 62' construction update
The month of February delivered some important additions At the start of the month, we brought her outside for the installation of her aft fuel tank, gyro, and finally, her cabin. Posted on 3 Mar
Bayliss 62' construction update
The cockpit has made quite the transformation The cockpit on Bayliss 62' made quite the transformation in January. At the beginning of the month, her faux teak half round was painted and the cockpit bulkhead received final primer. Posted on 9 Feb
Bayliss 78' Blue View construction update
January has been packed with teak installations within the interior January has been packed with teak installations within the interior of Blue View. Cabinetry fabrication and installation continues to progress. Everything from sofa bases to window trim and valances are in the works within the cabinetry shop. Posted on 7 Feb