Construction update: GameChanger - GameBoat 62'

by Bayliss Boatworks 10 Aug 2018 13:13 UTC
GameChanger, on the way to the paint bay © Bayliss Boatworks

Teak work on GameChanger continues! Our crew has finished her teak deck, as well as the remainder of the cockpit teak component installations - coverboards and coaming. As for her faux teak, the toe rail, drip molding, transom, and helm pod were all completed this month!

The cockpit area is truly coming to life, as the mezzanine lids are primed, fit, installed, and gas shocked.

On the interior, we've installed the dinette, and are beginning to mock up the greater salon area, cut sofa bases, and fabricate the companionway stairs and salon door. The main electrical panel is complete, while mechanical systems are being finalized and hooked up in the engine room, as well as in the engine room companionway. Today, GameChanger heads to our paint bay for topcoat. And, you guessed it - we've started our sea trial checklist. She'll be in the water very soon!

Read more about GameBoat 62' here

Related Articles

Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids. Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled This past month, we assembled the hull jig for our latest project: Bayliss 64'. Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75' The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun. Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
June was a productive month for our exterior carpentry team June was a productive month for our exterior carpentry team on the walkaround build. Posted on 1 Jul 2023