Bayliss Boatworks construction update: Blue View - Bayliss 78'

by John Bayliss 8 Mar 2020 13:04 UTC

The interior of Blue View progressed in leaps and bounds over the course of February.

The galley floor is now complete, padded panel installations are under way within the lower levels, and granite countertops have just been installed within the galley and lower levels. All overhead lighting is wired and hanging, soon to be mounted within the ceiling.

Fabrication of the crew stairs, day head and salon floors is now under way within our cabinetry shop. Next weekend, the salon windows will be tinted.

Over the course of the next month, the electrical crew will finalize all wiring and install lighting and receptacles within the hanging lockers.

Our mechanical crew is making the final preparations for Blue View's first sea trial in early March.

Read more about Blue View here

Related Articles

Bayliss Boatworks new construction updates
The latest 75' build at Bayliss Boatworks: Big Deal We are excited to debut the name of the latest 75' build at Bayliss Boatworks: Big Deal. Posted today at 7:40 pm
Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids. Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled This past month, we assembled the hull jig for our latest project: Bayliss 64'. Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75' The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun. Posted on 2 Aug 2023