by John Bayliss 3 Nov 2019 18:47 UTC

The "whiskey plank" is a benchmark in the build process that we always look forward to around here.

Traditionally and historically, once the final board is fastened to complete the hull planking process, a celebration would take place. In our hull shop, we just go back to work- but we always take a team photo, and everyone always signs the last plank.

In October, Bayliss 72' rounded the corner on this benchmark and our hull carpentry crew continued to hit the ground running.

With the planking complete and the hull sanded smooth, the carpentry crew prepared and shaped the shear line for the teak boards which were installed in October. Once the shear boards were installed, the crew built and shaped the spray rails, glassing the area where they would be mounted. On the transom, the zinc compartment was cut and glassed.

Once the spray rails are installed, the hull will be ready for glassing and fairing. Bayliss 72' is slated to flip before the year's end!

Across the street from the hull shop, Bayliss 72's cabin is nearly ready to be transported outside to cure. The bridge to cockpit access was cut from the bridge deck and the console and benchseats are faired and nearly ready for primer.

Read more about Bayliss 72' here

Related Articles

Bayliss Boatworks new construction updates
The latest 75' build at Bayliss Boatworks: Big Deal We are excited to debut the name of the latest 75' build at Bayliss Boatworks: Big Deal. Posted on 3 May
Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids. Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled This past month, we assembled the hull jig for our latest project: Bayliss 64'. Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75' The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun. Posted on 2 Aug 2023