Bayliss Boatworks construction update: Bayliss 75'

by Bayliss Boatworks 4 Nov 2020 16:17 UTC

After her flip right side up in September, the interior of Bayliss 75' was insulated, planked, and glassed inside our Hull Shop. Next, her three main bulkheads were fabricated, installed, and securely glassed into place.

With the bulkheads installed, the frame work was laid for the machinery spaces to begin taking shape. Over the course of the last month, our Hull Carpentry Crew constructed the machine tunnel, forward fuel tank surround, and strut blocking. At the month's end, the lazarette bulkhead was installed.

Inside Bayliss 75's pump room, the pump shelf is in the beginning stages of fabrication. Just forward of the pump room bulkhead, the water tank was built, installed and glassed in.

Last month, the bow thruster tube was installed, glassed, and is now in fairing. The sea chests were also fitted and glassed in within the lazarette. The engine room just received the final layer of glass, further reinforcing the foundation for a strong and sound hull.

In late October, Bayliss 75' transitioned across the street to the Construction Bay where it is now in the hands of the Exterior Carpentry Crew. This month, the crew's attention will turn to developing battery boxes and generator shelves for the pump room and engine room.

Read more about Bayliss 75’ here...

Related Articles

Bayliss 62' Seven construction update
Seven is geared to fish efficiently as possible In late November, Bayliss Boatworks delivered its most recent build to its owners, the 62-foot Seven; the first owners to enjoy two BBW christenings. Posted on 3 Dec 2020
Bayliss 67' Overtime construction update
The cabin has transitioned from glass, to epoxy, to fairing In October, the cabin for Overtime (Bayliss 67') transitioned from glass, to epoxy, to fairing. As the cabin progressed through rounds of sanding, work also began on the flybridge. Posted on 5 Nov 2020
Bayliss 72' Old Reliable construction update
Getting to the stage in the build process where things seem to develop at a rapid pace Old Reliable (Bayliss 72') is getting to the stage in the build process where things seem to develop at a rapid pace. In late October, she transitioned to our make-ready bay where our Exterior Carpentry work continues within the cockpit. Posted on 3 Nov 2020
Bayliss 62' Seven construction update
Getting close to her christening date! In October, our department supervisors gathered in the cockpit to depart on Seven's first sea trial. She performed beautifully, surpassing our expectations for speed, even before running gear finalizations. Posted on 2 Nov 2020
Bayliss 75 construction update
The hull sides were glassed, coated in epoxy, faired, and primed September was a month of rapid change on the exterior of Bayliss 75'. With her engine vents installed, the hull sides were glassed, coated in epoxy, faired, and primed. Posted on 6 Oct 2020
Bayliss 72' Old Reliable construction update
Color sanding on the hull sides and cabin is now under way On Old Reliable, the most striking change you'll notice is the bow deck. In September, the toe rail was installed before the entire deck was coated in primer. Posted on 4 Oct 2020
Bayliss 62' Seven construction update
Seven's custom transom artwork was completed by Everett Nautical In late September, Seven emerged from the paint bay with the hull glistening in final paint, and the cabin wrapped for protection. The crane arrived and our crews assisted Palm Beach Towers with the seamless installation of the tower and hard top. Posted on 2 Oct 2020
Bayliss 75 construction update
After prepping the hull, glassing began After celebrating Bayliss 75's "whiskey plank" in July, the planking screws were removed and filled with golf tees, then cut and sanded smooth. After prepping the hull, glassing began. Posted on 7 Sep 2020
Bayliss 72' Old Reliable construction update
The bow deck on Old Reliable really took shape over the course of the last month The bow deck on Old Reliable (Bayliss 72') really took shape over the course of the last month. Once planking was completed, the bow deck was glassed, coated in ad tech, and faired. Posted on 5 Sep 2020
Bayliss 62' Seven construction update
On the home stretch with the Paint & Fair Crew hard at work Seven (Bayliss 62') is in the home stretch! In late August, she moved into our paint bay where she received final paint. Our Paint & Fair Crew began their work with the application of a custom-blended shade of Imron "Cool Blue" on Seven's hull. Posted on 3 Sep 2020