Please select your home edition
Edition

Bayliss Boatworks construction update: Bayliss 75'

by Bayliss Boatworks 6 Oct 2020 17:56 UTC

September was a month of rapid change on the exterior of Bayliss 75'. With her engine vents installed, the hull sides were glassed, coated in epoxy, faired, and primed.

Once this work was complete, she was prepared for one of the most notorious benchmarks in the cold-molded build process- the hull flip.

View a time-lapse video of that process below.

Flipped right side up, Bayliss 75' was returned to the hands of the Hull Carpentry Crew where interior glassing has begun. In early October, she will see the installation of bulkheads, which will be quickly followed by side insulation and development of the machinery spaces.

Read more about Bayliss 75’ here...

Related Articles

Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids. Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled This past month, we assembled the hull jig for our latest project: Bayliss 64'. Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75' The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun. Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
June was a productive month for our exterior carpentry team June was a productive month for our exterior carpentry team on the walkaround build. Posted on 1 Jul 2023