Bayliss Boatworks construction update: Bayliss 72'

by John Bayliss 5 Feb 05:45 UTC
Bayliss 72' © John Bayliss

After Bayliss 72' was flipped and returned to the hull carpentry shop, work on the hull progressed quickly. The bow thruster tube was cut, installed, and is now in adtech. The sea chests were also fitted and glassed in.

Throughout the month of January, the hull's interior bottom received layers of glassing while bulkheads were fabricated. Once glassing was complete, the hull carpentry crew installed three bulkheads.

Work on the strut blocking, machine tunnel, and forward fuel tank surround is now under way. We're also moving forward with the fabrication of the the water tank and holding tank.

Read more about Bayliss 72' here.

Related Articles

Bayliss 75' construction update
Continuing to take shape in the Bayliss Boatworks hull shop Bayliss 75' is continuing to take shape in our hull shop. Once the hull jig was assembled, our crews wasted no time, beginning the steady process of shaping and laminating the bow stem. Posted on 12 Jul
Bayliss 72' Old Reliable construction update
With interior walls secured, installation of her carlings begins Old Reliable (Bayliss 72') had another eventful month. With interior walls secured in June, our crew was able to turn their attention to the installation of her carlings. Next week, bow deck planking will begin. Posted on 10 Jul
Bayliss 62' Seven construction update
The entire mezzanine now faired and ready for primer The month of June was all about fairing and priming on Seven (Bayliss 62'). Over the last month, the cockpit has continued to develop. The overhang ceiling was constructed and the grill center was built. Posted on 9 Jul
Bayliss 27' Center Consoles construction update
Commissioned by the owners of Blank Check (Bayliss 75') Commissioned by the owners of Blank Check (Bayliss 75'), we began building two 27-foot center consoles in the late summer of 2019 and this month, they are ready for delivery! Posted on 7 Jul
Salty Tiger - Bayliss 62' construction update
Set to be delivered this month While it's her custom transom artwork that has garnered the most attention, she also features a teak cockpit deck and coverboards, constructed from hand-selected teak boards. Posted on 6 Jul
Bayliss 75' construction update
The cabin has been coated in adtech and sanded down for fairing At the end of May, the hull jig was constructed. Our hull carpentry crew will now begin shaping the bow stem, closely followed by in the installation of the chine, sheer, and stringers. Posted on 10 Jun
Old Reliable - Bayliss 72' construction update
With walls in place, we see a first glimpse of the lower-level layout The forward area has taken shape- interior walls are up! With walls in place, we are seeing our first live glimpse of the lower-level layout, which will be comprised of four staterooms and three heads. Posted on 8 Jun
Bayliss 62' construction update
'Seven's bow deck, cabin and flybridge transition from fairing to final primer The exterior carpentry crew continues to develop the mezzanine and engine room companionway. Mezzanine stainless refrigerator/freezer liners are nearly ready for installation in the mezzanine and have already been installed on the flybridge. Posted on 6 Jun
Bayliss 62' construction update
Salty Tiger is approaching her delivery date Salty Tiger is approaching her delivery date as we move into June. In mid-May, after her first sea trial, she revealed her top speed to be over 47-knots, yielding a 41-knot cruise at 2150; the same as her sister ship, Tarheel (Bayliss 62'). Posted on 4 Jun
Blue View - Bayliss 78' construction update
A product of over 71,000 man hours and nearly 30 months of labor Blue View is powered with MTU M96L 16V engines, each with 2,600 horsepower. Her top speed was registered at over 44 knots at completion. This top end speed translates to a 37.5-knot cruise at 2150. Posted on 2 Jun