by John Bayliss 10 Jan 2020 14:20 UTC
Bayliss 62' © John Bayliss
With mezzanine build-out complete, our paint and fair department has taken over the cockpit, fairing and prepping every surface to receive primer.
While fairing is under way, our exterior carpentry crew is fabricating and glassing the mezzanine lids. Teak deck planking is ready to be laid in the cockpit once the paint is complete. Faux teak paint was just applied to the toe rail before being covered for protection.
Within the interior, our electrical crew is completing lighting and lower level wire pulls. The interior carpentry department is in the process of installing galley cabinetry and fabricating everything from bunks to night stands.