Bayliss Boatworks new construction update: Bayliss 62'

by John Bayliss 4 Nov 2019 16:49 UTC

Once she was flipped right side up in September, the interior of Bayliss 62' was glassed and things began to take shape in the engine room and pump room.

In the engine room, the hull carpentry crew has built and installed the battery boxes and generator shelves, glassing them in late October. Across the street in the metal works shop, the salon deck frame is already in the works.

Inside the pump room, the pump shelf is in the beginning stages of fabrication. Just forward of the pump room bulkhead, the water tank was built, installed and glassed in.

Read more about Bayliss 72' here

Related Articles

Bayliss 62' construction update
The cockpit has made quite the transformation The cockpit on Bayliss 62' made quite the transformation in January. At the beginning of the month, her faux teak half round was painted and the cockpit bulkhead received final primer. Posted on 9 Feb
Bayliss 78' Blue View construction update
January has been packed with teak installations within the interior January has been packed with teak installations within the interior of Blue View. Cabinetry fabrication and installation continues to progress. Everything from sofa bases to window trim and valances are in the works within the cabinetry shop. Posted on 7 Feb
Bayliss 72' construction update
Bow thruster tube cut, installed, and is now in adtech After Bayliss 72' was flipped and returned to the hull carpentry shop, work on the hull progressed quickly. The bow thruster tube was cut, installed, and is now in adtech. The sea chests were also fitted and glassed in. Posted on 5 Feb
Bayliss 62' construction update
The interior is beginning to take shape The interior of Bayliss 62' is beginning to take shape! In late January, with the engines and salon deck installed, our crew secured the anchor locker bulkhead and glassed the hull's interior sides. Posted on 3 Feb
Bayliss 62' construction update
With mezzanine build-out complete, the paint and fair dept has taken over With mezzanine build-out complete, our paint and fair department has taken over the cockpit, fairing and prepping every surface to receive primer. Posted on 10 Jan
Blue View - Bayliss 78' construction update
Upper mezzanine and cockpit bulkhead in final clear coat With the upper mezzanine and cockpit bulkhead in final clear coat, cabinetry installations have continued within the interior of Blue View. Bed frames are installed, head shower doors have been hung, and the salon sofa build-out is underway. Posted on 9 Jan
Bayliss 62' construction update
Machine tunnel and engine room moved into top coat In early December, Bayliss 62's machine tunnel and engine room moved into top coat. Bracing was added to the top of the forward fuel tank in preparation for deck installations. Posted on 7 Jan
Bayliss 72' construction update
December was a month of rapid change for the exterior of the boat December was a month of rapid change for the exterior of Bayliss 72'. With her engine vents installed, the hull sides were glassed, coated in adtech, faired, and primed. At the start of the new year, she was braced and prepared for today's hull flip. Posted on 5 Jan
Blue View - Bayliss 78' construction update
Blue View's cockpit bulkhead will soon receive the final coat of clear coat With her tower and hard top installed, Blue View has been nestled in our "make-ready" bay as our crews work on finalizing her exterior paint and installing her interior cabinetry. Posted on 6 Nov 2019
Bayliss 62' flybridge construction update
Crew now turning their attention to the preliminary half round layout The black mask outline was applied in late October and the crew is now turning their attention to the preliminary half round layout, which will be installed later this month. Posted on 5 Nov 2019
Nanni Diesel Australia 2020 - FOOTERMarina Exchange FOOTER 1Raymarine AUS Element HV FOOTER