Bayliss Boatworks new construction update: Bayliss 62'

by John Bayliss 4 Nov 2019 16:49 UTC

Once she was flipped right side up in September, the interior of Bayliss 62' was glassed and things began to take shape in the engine room and pump room.

In the engine room, the hull carpentry crew has built and installed the battery boxes and generator shelves, glassing them in late October. Across the street in the metal works shop, the salon deck frame is already in the works.

Inside the pump room, the pump shelf is in the beginning stages of fabrication. Just forward of the pump room bulkhead, the water tank was built, installed and glassed in.

Read more about Bayliss 72' here

Related Articles

Bayliss 75' construction update
The console transitioned from jig, to core-cell, to glass, and is currently in ad tech Cabin glassing on Bayliss 75' was completed in mid-April, after which our crew turned their attention to fabricating the flybridge and console. Posted on 7 May
Salty Tiger - Bayliss 62' construction update
Cabinetry installations have quickly progressed In early April, Salty Tiger's transom artwork was encased in layer upon layer of clear coat. On the interior, cabinetry installations have quickly progressed. Posted on 6 May
Old Reliable - Bayliss 72' construction update
The engine room transitioned from adtech to fairing Old Reliable's engine room and pump room underwent quite the transformation over the month of April. The engine room transitioned from adtech to fairing, and after several rounds of sanding, finally primer. Posted on 5 May
Seven - Bayliss 62' construction update
Both the toe rail and cockpit deck were installed on Seven! In April, both the toe rail and cockpit deck were installed on Seven! Throughout the latter half of the month, the toe rail underwent glassing, fairing and adtech. Posted on 4 May
Blue View - Bayliss 78' construction update
Inching closer to her delivery later this month Our crews have been hitting big milestones on Blue View! We are seeing finalizations daily as we inch closer to her delivery later this month. Posted on 3 May
Newest Project: Bayliss 75' construction update
Cabin glassing began at the end of March We began our newest project, Bayliss 75', on February 28th. Throughout the month of March, our hull carpentry crew completed the cabin jig, mahogany carlins, and core-cell planking. Posted on 9 Apr
Salty Tiger - Bayliss 62' construction update
Within the galley lower cabinetry has been installed With Salty Tiger returned to the make-ready bay with her full paint complete, our interior carpentry crew wasted no time getting back onto the vessel to begin cabinetry installations. Posted on 7 Apr
Old Reliable - Bayliss 72' construction update
The machine tunnel is now completely in primer In late March, the forward fuel tank was installed, allowing our hull carpentry crew to complete the surrounding chases and prepare for the installation of the lower sole. Posted on 5 Apr
Seven - Bayliss 62' construction update
Over the course of March, the bow deck was planked and glassed With Seven's aft fuel tank, gyro and cabin installations complete, our exterior carpentry crew turned their focus to planking the bow deck and developing the flybridge arrangement. Posted on 3 Apr
Blue View - Bayliss 78' construction update
The month of March made things real for Blue View At the month's end, Blue View's transom artwork (protected by nearly a dozen coats of clear coat), bootstripe, and bottom paint were unveiled. Posted on 2 Apr