Construction updates - Gypsea Bayliss 62'

by Bayliss Boatworks 8 Apr 2019 15:27 UTC
Gypsea Bayliss 62' © Bayliss Boatworks

Our hull carpentry department has been busy with Gypsea (Bayliss 62'). Following the installation of her forward fuel tank in February, our crew turned their attention to building out the machine tunnel, pump shelf, engine room, forward sole, and lazarette area.

In late March, the forward pump room deck was installed and her cabin was transported outside to post-cure.

She is nearly ready to be outfitted with her main mechanical components. By next month, Gypsea will receive twin V12 MAN 1550 engines and two 25kw Northern Lights generators. Once these main components are installed, interior wall construction will begin. Built with fishing as a priority, Gypsea's general arrangement will consist of three staterooms, two heads, and a tackle/freezer room.

Read more about Gypsea here >>>

Related Articles

Bayliss 75' construction update
The console transitioned from jig, to core-cell, to glass, and is currently in ad tech Cabin glassing on Bayliss 75' was completed in mid-April, after which our crew turned their attention to fabricating the flybridge and console. Posted on 7 May
Salty Tiger - Bayliss 62' construction update
Cabinetry installations have quickly progressed In early April, Salty Tiger's transom artwork was encased in layer upon layer of clear coat. On the interior, cabinetry installations have quickly progressed. Posted on 6 May
Old Reliable - Bayliss 72' construction update
The engine room transitioned from adtech to fairing Old Reliable's engine room and pump room underwent quite the transformation over the month of April. The engine room transitioned from adtech to fairing, and after several rounds of sanding, finally primer. Posted on 5 May
Seven - Bayliss 62' construction update
Both the toe rail and cockpit deck were installed on Seven! In April, both the toe rail and cockpit deck were installed on Seven! Throughout the latter half of the month, the toe rail underwent glassing, fairing and adtech. Posted on 4 May
Blue View - Bayliss 78' construction update
Inching closer to her delivery later this month Our crews have been hitting big milestones on Blue View! We are seeing finalizations daily as we inch closer to her delivery later this month. Posted on 3 May
Newest Project: Bayliss 75' construction update
Cabin glassing began at the end of March We began our newest project, Bayliss 75', on February 28th. Throughout the month of March, our hull carpentry crew completed the cabin jig, mahogany carlins, and core-cell planking. Posted on 9 Apr
Salty Tiger - Bayliss 62' construction update
Within the galley lower cabinetry has been installed With Salty Tiger returned to the make-ready bay with her full paint complete, our interior carpentry crew wasted no time getting back onto the vessel to begin cabinetry installations. Posted on 7 Apr
Old Reliable - Bayliss 72' construction update
The machine tunnel is now completely in primer In late March, the forward fuel tank was installed, allowing our hull carpentry crew to complete the surrounding chases and prepare for the installation of the lower sole. Posted on 5 Apr
Seven - Bayliss 62' construction update
Over the course of March, the bow deck was planked and glassed With Seven's aft fuel tank, gyro and cabin installations complete, our exterior carpentry crew turned their focus to planking the bow deck and developing the flybridge arrangement. Posted on 3 Apr
Blue View - Bayliss 78' construction update
The month of March made things real for Blue View At the month's end, Blue View's transom artwork (protected by nearly a dozen coats of clear coat), bootstripe, and bottom paint were unveiled. Posted on 2 Apr