Construction updates: Tarheel Bayliss 62' - Team is racing past construction benchmarks

by Bayliss Boatworks 6 Apr 19:55 UTC
Tarheel Bayliss 62' © Bayliss Boatworks

Our team is racing past construction benchmarks on Tarheel. Now blanketed in final primer, the faux teak drip-molding helm pod, and toe rail were installed in March, which has really brought her exterior appearance to life.

As for the cockpit, it's progressing at a rapid pace. The teak coverboards were installed in late March and the teak cockpit deck is currently under way. The tuna door is being fitted, and the Gameboat crew is gas-shocking mezzanine lids.

On Tarheel's interior, our electrical department is in the process of wiring the transformers and finalizing the bridge panel. The interior cabinetry department has been hard at work on the upper and lower level cabinetry, installing everything from galley cabinetry to stateroom bunks. Soon, the granite countertops will be patterned and cut.

Our mechanical crew is in the process of installing all pump room components and finalizing the air handlers and chiller lines. The machine tunnel is nearly complete, and both fuel tanks are hooked up. Next on our crew's list is the installation of the main engine exhaust, bow thruster motor and a Willy Vac® system for the engine room.

Read more about Tarheel here >>>

Related Articles

Construction updates - Gypsea Bayliss 62'
Carlings and cabin go in With her interior walls installed, our crew was able to turn their attention to the installation of her carlings. Shortly after, she checked off another benchmark in the build process- the installation of her cabin. Posted on 7 Jun
Construction updates - Blue View Bayliss 78'
May brought several new teak additions to Blue View On the flybridge, her console is now in final primer. The cabin, bridge, and hull are in the process of being sanded and will soon match the console in final primer. Posted on 5 Jun
Construction updates - Tarheel Bayliss 62'
Emerging from the paint bay looking like a finished boat Tarheel also received her transom paint last month, courtesy of Everett Nautical. Our paint crew will focus on applying her waterline and bottom paint over the next couple of weeks. Posted on 3 Jun
Blank Check (Bayliss 75') delivered
Powered with MTU 16V2000 M9L engines, each with 2,600 horsepower The 75' Blank Check was christened and delivered to her owners in early April. A product of over 68,000 man-hours and nearly 28 months of labor, she will be spending much of her time at southern latitudes. Posted on 11 May
Construction updates - Tarheel Bayliss 62'
Tarheel (Bayliss 62') is now in the home stretch. While the interior carpentry crew continues to work on lower and upper level installs, our metal works department is creating a brand new custom TV lift for the salon. Posted on 9 May
Construction updates - Blue View Bayliss 78'
We hit some serious benchmarks on Blue View's appearance in April. The most dramatic was the installation of her teak toe rail. Work continues on the mezzanine, where the exterior carpentry crew is currently installing five custom stainless steel freezer boxes. Posted on 7 May
Construction updates - Gypsea Bayliss 62'
We checked off several big installations in April Once her engine room was faired and primed, our mechanical crew installed her twin V12 MAN 1550 engines, two 25kw Northern Lights generators, and a Seakeeper 9 before closing everything in with the salon deck. Posted on 5 May
Construction updates - Gypsea Bayliss 62'
The hull carpentry department has been busy with Gypsea (Bayliss 62') Following the installation of her forward fuel tank in February, our crew turned their attention to building out the machine tunnel, pump shelf, engine room, forward sole, and lazarette area. Posted on 8 Apr
Construction updates: Blue View Bayliss 78'
The Crew has begun installing custom stainless steel liners Now that Blue View's cabin and flybridge are in primer, her exterior window molding has been installed and the exterior carpentry crew is in the process of laying out the toe rail. Posted on 7 Apr
Construction updates: Bayliss 75'
It's christening month! While the exterior appearance of this build was finalized in March with the addition of her buggy top, we are seeing changes on the interior daily. Posted on 6 Apr