Construction update: Blue View - Bayliss 78'

by Bayliss Boatworks 6 Mar 16:15 UTC
Blue View - Bayliss 78' © John Bayliss

Blue View (Bayliss 78'), has also experienced major progress on the bridge. Fairing and primer were applied to the bow and cabin exterior in early February and our paint crew is now tackling rounds of spot fairing and sanding.

The flybirdge is changing quick! Once the space was glassed in February, the bench seats and brow wall underwent their own rounds of fairing and primer. With the console installed, work begins on the raised teak deck- a unique feature to this build, sure to be a stunner!

The cockpit has been a bustle of activity as well. The cockpit deck and coverboards were glassed, allowing the exterior carpentry crew to turn their attention to building the mezzanine walls.

Our in-house design department has finalized the layouts for the master, guest, and VIP, and crew staterooms. Now, our cabinetry crew is beginning mock-ups in each space, bringing a real visual cohesiveness to the lower level. Our mechanical crew has completed the hydraulics in the engine room and they are now turning their attention to the installation of the holding tank and chiller units.

Custom stainless steel hawse pipes are being developed by our metal works department this month. Stainless steel liners are also being fabricated for the flybridge and mezzanine. Blue View will hold large refrigerated boxes in the bridge console with a drink box in the forward bridge seating compartment- along with five refrigerated boxes in the mezzanine.

Read more about Blue View here >>>

Related Articles

Blank Check (Bayliss 75') delivered
Powered with MTU 16V2000 M9L engines, each with 2,600 horsepower The 75' Blank Check was christened and delivered to her owners in early April. A product of over 68,000 man-hours and nearly 28 months of labor, she will be spending much of her time at southern latitudes. Posted on 11 May
Construction updates - Tarheel Bayliss 62'
Tarheel (Bayliss 62') is now in the home stretch. While the interior carpentry crew continues to work on lower and upper level installs, our metal works department is creating a brand new custom TV lift for the salon. Posted on 9 May
Construction updates - Blue View Bayliss 78'
We hit some serious benchmarks on Blue View's appearance in April. The most dramatic was the installation of her teak toe rail. Work continues on the mezzanine, where the exterior carpentry crew is currently installing five custom stainless steel freezer boxes. Posted on 7 May
Construction updates - Gypsea Bayliss 62'
We checked off several big installations in April Once her engine room was faired and primed, our mechanical crew installed her twin V12 MAN 1550 engines, two 25kw Northern Lights generators, and a Seakeeper 9 before closing everything in with the salon deck. Posted on 5 May
Construction updates - Gypsea Bayliss 62'
The hull carpentry department has been busy with Gypsea (Bayliss 62') Following the installation of her forward fuel tank in February, our crew turned their attention to building out the machine tunnel, pump shelf, engine room, forward sole, and lazarette area. Posted on 8 Apr
Construction updates: Blue View Bayliss 78'
The Crew has begun installing custom stainless steel liners Now that Blue View's cabin and flybridge are in primer, her exterior window molding has been installed and the exterior carpentry crew is in the process of laying out the toe rail. Posted on 7 Apr
Construction updates - Tarheel Bayliss 62'
The team is racing past construction benchmarks As for the cockpit, it's progressing at a rapid pace. The teak coverboards were installed in late March and the teak cockpit deck is currently under way. The tuna door is being fitted, and the Gameboat crew is gas-shocking mezzanine lids. Posted on 6 Apr
Construction updates: Bayliss 75'
It's christening month! While the exterior appearance of this build was finalized in March with the addition of her buggy top, we are seeing changes on the interior daily. Posted on 6 Apr
Construction update: Gypsea - Bayliss 62'
Forward fuel tank installed, machine tunnel buildout and framing progressed quickly With the forward fuel tank installed, machine tunnel buildout and framing progressed quickly. Our crew is currently fabricating the windlass and bow-thruster battery box, holding tank, and water tank. Posted on 7 Mar
Construction update: Tarheel - Bayliss 62'
The entire flybridge on Tarheel is now in final primer This month, her faux teak drip-molding will be sighted and installed- a defining feature of the cabin which will really bring the exterior appearance together. Posted on 5 Mar