Construction update: Blue View - Bayliss 78'

by Bayliss Boatworks 6 Mar 2019 16:15 UTC
Blue View - Bayliss 78' © John Bayliss

Blue View (Bayliss 78'), has also experienced major progress on the bridge. Fairing and primer were applied to the bow and cabin exterior in early February and our paint crew is now tackling rounds of spot fairing and sanding.

The flybirdge is changing quick! Once the space was glassed in February, the bench seats and brow wall underwent their own rounds of fairing and primer. With the console installed, work begins on the raised teak deck- a unique feature to this build, sure to be a stunner!

The cockpit has been a bustle of activity as well. The cockpit deck and coverboards were glassed, allowing the exterior carpentry crew to turn their attention to building the mezzanine walls.

Our in-house design department has finalized the layouts for the master, guest, and VIP, and crew staterooms. Now, our cabinetry crew is beginning mock-ups in each space, bringing a real visual cohesiveness to the lower level. Our mechanical crew has completed the hydraulics in the engine room and they are now turning their attention to the installation of the holding tank and chiller units.

Custom stainless steel hawse pipes are being developed by our metal works department this month. Stainless steel liners are also being fabricated for the flybridge and mezzanine. Blue View will hold large refrigerated boxes in the bridge console with a drink box in the forward bridge seating compartment- along with five refrigerated boxes in the mezzanine.

Read more about Blue View here >>>

Related Articles

Bayliss 75' construction update
The cabin has been coated in adtech and sanded down for fairing At the end of May, the hull jig was constructed. Our hull carpentry crew will now begin shaping the bow stem, closely followed by in the installation of the chine, sheer, and stringers. Posted on 10 Jun
Old Reliable - Bayliss 72' construction update
With walls in place, we see a first glimpse of the lower-level layout The forward area has taken shape- interior walls are up! With walls in place, we are seeing our first live glimpse of the lower-level layout, which will be comprised of four staterooms and three heads. Posted on 8 Jun
Bayliss 62' construction update
'Seven's bow deck, cabin and flybridge transition from fairing to final primer The exterior carpentry crew continues to develop the mezzanine and engine room companionway. Mezzanine stainless refrigerator/freezer liners are nearly ready for installation in the mezzanine and have already been installed on the flybridge. Posted on 6 Jun
Bayliss 62' construction update
Salty Tiger is approaching her delivery date Salty Tiger is approaching her delivery date as we move into June. In mid-May, after her first sea trial, she revealed her top speed to be over 47-knots, yielding a 41-knot cruise at 2150; the same as her sister ship, Tarheel (Bayliss 62'). Posted on 4 Jun
Blue View - Bayliss 78' construction update
A product of over 71,000 man hours and nearly 30 months of labor Blue View is powered with MTU M96L 16V engines, each with 2,600 horsepower. Her top speed was registered at over 44 knots at completion. This top end speed translates to a 37.5-knot cruise at 2150. Posted on 2 Jun
Bayliss 75' construction update
The console transitioned from jig, to core-cell, to glass, and is currently in ad tech Cabin glassing on Bayliss 75' was completed in mid-April, after which our crew turned their attention to fabricating the flybridge and console. Posted on 7 May
Salty Tiger - Bayliss 62' construction update
Cabinetry installations have quickly progressed In early April, Salty Tiger's transom artwork was encased in layer upon layer of clear coat. On the interior, cabinetry installations have quickly progressed. Posted on 6 May
Old Reliable - Bayliss 72' construction update
The engine room transitioned from adtech to fairing Old Reliable's engine room and pump room underwent quite the transformation over the month of April. The engine room transitioned from adtech to fairing, and after several rounds of sanding, finally primer. Posted on 5 May
Seven - Bayliss 62' construction update
Both the toe rail and cockpit deck were installed on Seven! In April, both the toe rail and cockpit deck were installed on Seven! Throughout the latter half of the month, the toe rail underwent glassing, fairing and adtech. Posted on 4 May
Blue View - Bayliss 78' construction update
Inching closer to her delivery later this month Our crews have been hitting big milestones on Blue View! We are seeing finalizations daily as we inch closer to her delivery later this month. Posted on 3 May