Please select your home edition
Edition

Construction update: Tarheel - Bayliss 62'

by Bayliss Boatworks 5 Mar 2019 14:41 UTC
Tarheel - Bayliss 62' © John Bayliss

The entire flybridge on Tarheel (Bayliss 62') is now in final primer, including the console and benchseat lids. Her shiny new faux teak helm pod was installed in late February.

This month, her faux teak drip-molding will be sighted and installed- a defining feature of the cabin which will really bring the exterior appearance together.

Mechanically, our crew has been tackling air handlers and chiller line piping which are now installed and finalized. The machine tunnel is nearly complete, and both fuel tanks are hooked up. In the lower level areas, shower and sink plumbing is nearly complete. Much of the cabinetry in the lower level is installed including the stateroom bunks and dressers, as well as the dayhead vanity. In the cockpit area, the salon bulkhead has been installed, and mezzanine buildout continues. The tuna door has been cut and glassed as well.

Next on our crew's list is installation of chiller units, main engine exhaust, bow thruster motor and a Willy Vac® system for the engine room. On the interior, it won't be long before we begin to see the installation of head floors and various cabinetry in the tackle room and salon.

Read more about Tarheel here >>>

Related Articles

Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids. Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled This past month, we assembled the hull jig for our latest project: Bayliss 64'. Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75' The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun. Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
June was a productive month for our exterior carpentry team June was a productive month for our exterior carpentry team on the walkaround build. Posted on 1 Jul 2023