Construction update: Tarheel - Bayliss 62'

by Bayliss Boatworks 5 Mar 14:41 UTC
Tarheel - Bayliss 62' © John Bayliss

The entire flybridge on Tarheel (Bayliss 62') is now in final primer, including the console and benchseat lids. Her shiny new faux teak helm pod was installed in late February.

This month, her faux teak drip-molding will be sighted and installed- a defining feature of the cabin which will really bring the exterior appearance together.

Mechanically, our crew has been tackling air handlers and chiller line piping which are now installed and finalized. The machine tunnel is nearly complete, and both fuel tanks are hooked up. In the lower level areas, shower and sink plumbing is nearly complete. Much of the cabinetry in the lower level is installed including the stateroom bunks and dressers, as well as the dayhead vanity. In the cockpit area, the salon bulkhead has been installed, and mezzanine buildout continues. The tuna door has been cut and glassed as well.

Next on our crew's list is installation of chiller units, main engine exhaust, bow thruster motor and a Willy Vac® system for the engine room. On the interior, it won't be long before we begin to see the installation of head floors and various cabinetry in the tackle room and salon.

Read more about Tarheel here >>>

Related Articles

Construction updates: Gypsea Bayliss 62'
The month of June has been an especially busy one for our paint crew With the cabin installed on Gypsea (Bayliss 62'), our crew turned their attention to glassing, fairing, and priming the engine room companionway, aft fuel tank compartment and anchor locker. Posted on 7 Jul
Construction updates: Blue View - Bayliss 78'
Blue View's final teak component, the bulkhead, is now under development Blue View (Bayliss 78') is getting to that point in the process where benchmarks seem to be flying by at a rapid pace. Faired and sanded to perfection by our paint crew, she was blanketed in final primer in late June. Posted on 6 Jul
Construction updates - Bayliss 62'
In a stage of rapid progression With her hull jig assembled, our carpentry crew made quick work of constructing the keel, sheer and chine. Over the course of the last couple of weeks, the crew installed three layers of bottom planking. Posted on 5 Jul
Construction updates - Tarheel Bayliss 62'
Late June was an exciting time at the shop Our very own 62-foot build is getting close to her christening date! Late June was an exciting time at the shop. Department supervisors gathered in the cockpit on Tarheel (Bayliss 62') as we took her out for the first sea trial. Posted on 4 Jul
Construction updates - Gypsea Bayliss 62'
Carlings and cabin go in With her interior walls installed, our crew was able to turn their attention to the installation of her carlings. Shortly after, she checked off another benchmark in the build process- the installation of her cabin. Posted on 7 Jun
Construction updates - Blue View Bayliss 78'
May brought several new teak additions to Blue View On the flybridge, her console is now in final primer. The cabin, bridge, and hull are in the process of being sanded and will soon match the console in final primer. Posted on 5 Jun
Construction updates - Tarheel Bayliss 62'
Emerging from the paint bay looking like a finished boat Tarheel also received her transom paint last month, courtesy of Everett Nautical. Our paint crew will focus on applying her waterline and bottom paint over the next couple of weeks. Posted on 3 Jun
Blank Check (Bayliss 75') delivered
Powered with MTU 16V2000 M9L engines, each with 2,600 horsepower The 75' Blank Check was christened and delivered to her owners in early April. A product of over 68,000 man-hours and nearly 28 months of labor, she will be spending much of her time at southern latitudes. Posted on 11 May
Construction updates - Tarheel Bayliss 62'
Tarheel (Bayliss 62') is now in the home stretch. While the interior carpentry crew continues to work on lower and upper level installs, our metal works department is creating a brand new custom TV lift for the salon. Posted on 9 May
Construction updates - Blue View Bayliss 78'
We hit some serious benchmarks on Blue View's appearance in April. The most dramatic was the installation of her teak toe rail. Work continues on the mezzanine, where the exterior carpentry crew is currently installing five custom stainless steel freezer boxes. Posted on 7 May