New construction updates - Bayliss 75'

by Bayliss Boatworks 3 Mar 03:52 UTC
Bayliss 75' © Bayliss Boatworks

The month of February made things real for Bayliss 75' as this build nears completion. One of the biggest benchmarks was checked off in early February- her first sea trial.

After sea trials, Bayliss 75' was slid back inside the shop for her final paintwork while our cabinetry team continued work on her interior. She re-emerged last week with a striking red and gold water line and transom lettering. Our paint crew will now apply nearly a dozen coats of clear coat to the transom to seal the surface and accentuate the shine.

This close to the finish line, we're focusing on the hundreds of details that will make Bayliss 75' whole. Electronics, custom rod storage, soft goods, carpet, and much more are on our punch list as we get closer to her final launch date.

Look for delivery of Bayliss 75' in early spring of 2019

This build will be part of a two-boat program (as the larger of the owner's two boats), and the owner's second Bayliss hull.

Specifications:

  • Start Date: February 2017
  • Length: 75'
  • Beam: 20' 8"
  • Draft: 5' 10"
  • Power: (2) MTU M96L 16V @ 2,600 hp each
  • Gyro: Seakeeper 26
  • Genset: (2) 30kw Northern Lights
  • Fuel Capacity: 2,650 gallons
  • Water Capacity: 450 gallons
  • Water Maker: (2) 1,200 gal. per day and dockside treatment system
  • Holding Tank: 200 gal.
  • Interior Layout: 4 staterooms, 3.5 heads, Pantry
  • Cockpit Layout: Mezzanine Style Cockpit with Teak Aft Bulkhead
  • Bridge Layout: Center Console, Two Freezers, Two helm chairs
Read more about the Bayliss 75' here.

Related Articles

Construction updates - Gypsea Bayliss 62'
The hull carpentry department has been busy with Gypsea (Bayliss 62') Following the installation of her forward fuel tank in February, our crew turned their attention to building out the machine tunnel, pump shelf, engine room, forward sole, and lazarette area. Posted on 8 Apr
Construction updates: Blue View Bayliss 78'
The Crew has begun installing custom stainless steel liners Now that Blue View's cabin and flybridge are in primer, her exterior window molding has been installed and the exterior carpentry crew is in the process of laying out the toe rail. Posted on 7 Apr
Construction updates - Tarheel Bayliss 62'
The team is racing past construction benchmarks As for the cockpit, it's progressing at a rapid pace. The teak coverboards were installed in late March and the teak cockpit deck is currently under way. The tuna door is being fitted, and the Gameboat crew is gas-shocking mezzanine lids. Posted on 6 Apr
Construction updates: Bayliss 75'
It's christening month! While the exterior appearance of this build was finalized in March with the addition of her buggy top, we are seeing changes on the interior daily. Posted on 6 Apr
Construction update: Gypsea - Bayliss 62'
Forward fuel tank installed, machine tunnel buildout and framing progressed quickly With the forward fuel tank installed, machine tunnel buildout and framing progressed quickly. Our crew is currently fabricating the windlass and bow-thruster battery box, holding tank, and water tank. Posted on 7 Mar
Construction update: Blue View - Bayliss 78'
Blue View has experienced major progress on the bridge Once the space was glassed in February, the bench seats and brow wall underwent their own rounds of fairing and primer. With the console installed, work begins on the raised teak deck- a unique feature to this build, sure to be a stunner! Posted on 6 Mar
Construction update: Tarheel - Bayliss 62'
The entire flybridge on Tarheel is now in final primer This month, her faux teak drip-molding will be sighted and installed- a defining feature of the cabin which will really bring the exterior appearance together. Posted on 5 Mar
Construction update: Gypsea - GameBoat 62'
Anproductive January now that her hull is planked, glassed and faired At the end of January, our hull carpentry crew installed Gypsea's main bulkheads, and will soon begin on the buildout of her machine tunnel. Posted on 5 Feb
Construction update: Blue View - Bayliss 78'
Blue View (Bayliss 78') received her aft fuel tank Cockpit cabinetry and work on the mezzanine will be under way soon. On the flybridge, Blue View's console has been fabricated and installed. The bridge bench seats have been faired and are already receiving primer coats. Posted on 4 Feb
Construction update: Bayliss 75'
The interior of Bayliss 75' progressed in leaps and bounds In January, the exterior appearance of Bayliss 75' was inched one step closer to completion with the placement of her tower and hardtop as well as the installation of her teak salon door. Posted on 3 Feb