New construction updates - Bayliss 75'

by Bayliss Boatworks 3 Mar 03:52 UTC
Bayliss 75' © Bayliss Boatworks

The month of February made things real for Bayliss 75' as this build nears completion. One of the biggest benchmarks was checked off in early February- her first sea trial.

After sea trials, Bayliss 75' was slid back inside the shop for her final paintwork while our cabinetry team continued work on her interior. She re-emerged last week with a striking red and gold water line and transom lettering. Our paint crew will now apply nearly a dozen coats of clear coat to the transom to seal the surface and accentuate the shine.

This close to the finish line, we're focusing on the hundreds of details that will make Bayliss 75' whole. Electronics, custom rod storage, soft goods, carpet, and much more are on our punch list as we get closer to her final launch date.

Look for delivery of Bayliss 75' in early spring of 2019

This build will be part of a two-boat program (as the larger of the owner's two boats), and the owner's second Bayliss hull.

Specifications:

  • Start Date: February 2017
  • Length: 75'
  • Beam: 20' 8"
  • Draft: 5' 10"
  • Power: (2) MTU M96L 16V @ 2,600 hp each
  • Gyro: Seakeeper 26
  • Genset: (2) 30kw Northern Lights
  • Fuel Capacity: 2,650 gallons
  • Water Capacity: 450 gallons
  • Water Maker: (2) 1,200 gal. per day and dockside treatment system
  • Holding Tank: 200 gal.
  • Interior Layout: 4 staterooms, 3.5 heads, Pantry
  • Cockpit Layout: Mezzanine Style Cockpit with Teak Aft Bulkhead
  • Bridge Layout: Center Console, Two Freezers, Two helm chairs
Read more about the Bayliss 75' here.

Related Articles

Blank Check (Bayliss 75') delivered
Powered with MTU 16V2000 M9L engines, each with 2,600 horsepower The 75' Blank Check was christened and delivered to her owners in early April. A product of over 68,000 man-hours and nearly 28 months of labor, she will be spending much of her time at southern latitudes. Posted on 11 May
Construction updates - Tarheel Bayliss 62'
Tarheel (Bayliss 62') is now in the home stretch. While the interior carpentry crew continues to work on lower and upper level installs, our metal works department is creating a brand new custom TV lift for the salon. Posted on 9 May
Construction updates - Blue View Bayliss 78'
We hit some serious benchmarks on Blue View's appearance in April. The most dramatic was the installation of her teak toe rail. Work continues on the mezzanine, where the exterior carpentry crew is currently installing five custom stainless steel freezer boxes. Posted on 7 May
Construction updates - Gypsea Bayliss 62'
We checked off several big installations in April Once her engine room was faired and primed, our mechanical crew installed her twin V12 MAN 1550 engines, two 25kw Northern Lights generators, and a Seakeeper 9 before closing everything in with the salon deck. Posted on 5 May
Construction updates - Gypsea Bayliss 62'
The hull carpentry department has been busy with Gypsea (Bayliss 62') Following the installation of her forward fuel tank in February, our crew turned their attention to building out the machine tunnel, pump shelf, engine room, forward sole, and lazarette area. Posted on 8 Apr
Construction updates: Blue View Bayliss 78'
The Crew has begun installing custom stainless steel liners Now that Blue View's cabin and flybridge are in primer, her exterior window molding has been installed and the exterior carpentry crew is in the process of laying out the toe rail. Posted on 7 Apr
Construction updates - Tarheel Bayliss 62'
The team is racing past construction benchmarks As for the cockpit, it's progressing at a rapid pace. The teak coverboards were installed in late March and the teak cockpit deck is currently under way. The tuna door is being fitted, and the Gameboat crew is gas-shocking mezzanine lids. Posted on 6 Apr
Construction updates: Bayliss 75'
It's christening month! While the exterior appearance of this build was finalized in March with the addition of her buggy top, we are seeing changes on the interior daily. Posted on 6 Apr
Construction update: Gypsea - Bayliss 62'
Forward fuel tank installed, machine tunnel buildout and framing progressed quickly With the forward fuel tank installed, machine tunnel buildout and framing progressed quickly. Our crew is currently fabricating the windlass and bow-thruster battery box, holding tank, and water tank. Posted on 7 Mar
Construction update: Blue View - Bayliss 78'
Blue View has experienced major progress on the bridge Once the space was glassed in February, the bench seats and brow wall underwent their own rounds of fairing and primer. With the console installed, work begins on the raised teak deck- a unique feature to this build, sure to be a stunner! Posted on 6 Mar