Bayliss Boatworks Construction update: Gypsea - GameBoat 62'

by John Bayliss 5 Feb 15:27 UTC
Gypsea - GameBoat 62' © Bayliss Boatworks

Gypsea (GameBoat 62') had a productive January! Now that her hull is planked, glassed and faired, she checked off one of the biggest benchmarks in the build process- turning right side up.

At the end of January, our hull carpentry crew installed Gypsea's main bulkheads, and will soon begin on the buildout of her machine tunnel. Our in-house design department is working on finalizing various installation drawings, while our mechanical crew preps for the arrival of the main engine exhaust.

Read more about Gypsea here >>>

Related Articles

Construction update: Blue View - Bayliss 78'
Blue View (Bayliss 78') received her aft fuel tank Cockpit cabinetry and work on the mezzanine will be under way soon. On the flybridge, Blue View's console has been fabricated and installed. The bridge bench seats have been faired and are already receiving primer coats. Posted on 4 Feb
Construction update: Bayliss 75'
The interior of Bayliss 75' progressed in leaps and bounds In January, the exterior appearance of Bayliss 75' was inched one step closer to completion with the placement of her tower and hardtop as well as the installation of her teak salon door. Posted on 3 Feb
Blue View (Bayliss 78') gets aft fuel tank
Snuck outside as soon as the New Year began! Blue View (Bayliss 78') snuck outside for her aft fuel tank installation as soon as the New Year began! Posted on 8 Jan
Tarheel (GameBoat 62') cabinetry moving along
Bow deck and cabin are finally in finish primer Tarheel (GameBoat 62') looks different on the outside this month, as her bow deck and cabin are finally in finish primer. Posted on 7 Jan
Bayliss 75' shines in final paint
Emerging from her stay in the paint bay Bayliss 75' emerged from her stay in the paint bay, decked out in Cloud White. Posted on 6 Jan
GameChanger christened in early December
Bayliss Boatworks send their second GameBoat into the world In early December, Bayliss Boatworks sent their second GameBoat into the world with a proper christening. Posted on 5 Jan
Construction update: Gypsea - GameBoat 62'
And just like that, our fourth GameBoat is planked! At November's end, our hull construction crew placed the Whiskey Plank on Gypsea. During November, we managed to complete tunnel construction, install shaft tubes, and begin blocking for the bow thruster. Posted on 12 Dec 2018
Construction update: Tarheel - GameBoat 62'
On Tarheel, our interior crew is making incredible progress On Tarheel, our interior crew is making incredible progress, as buildout in all lower level spaces has begun. The Master stateroom will feature matching bunks on the port and starboard sides, with ample storage above. Posted on 10 Dec 2018
Construction update: Blue View - Bayliss 78'
The interior is beginning to look alive on this incredibly intricate build After the sizable change to the exterior with the addition of the cabin, our crew's attention now turns inward. The lower level buildout and transformation has begun, really demonstrating the size of Blue View - as it houses four staterooms quite easily. Posted on 8 Dec 2018
Construction update: Bayliss 75'
December will be an exciting month for the boat! Teak wainscoting is being installed along the spacious companionway, where the pattern is bold and impressive - a seamless match for the remainder of the teak patterns throughout this build. Posted on 6 Dec 2018
Marina Exchange FOOTER 1Raymarine AUS 2018 Aug - Axiom - Footer