by John Bayliss 12 Dec 2018 15:47 UTC
The 62' Gypsea, planking in progress © Bayliss Boatworks

And just like that, our fourth GameBoat is planked! At November's end, our hull construction crew placed the Whiskey Plank on Gypsea. During November, we managed to complete tunnel construction, install shaft tubes, and begin blocking for the bow thruster.

Now, our crew begins to fabricate Gypsea's bulkheads so they are ready to install once she flips in the New Year.

The main cabin and bridge were affixed together in November, while the exterior transformed through fairing. Now, the cabin is now in primer! Our design crew is continuing to work on this build's general arrangement, along with finalizing mechanical layout and placement in the coming months.

Read more about Gypsea here >>>

Related Articles

Construction update: Gypsea - Bayliss 62'
Forward fuel tank installed, machine tunnel buildout and framing progressed quickly With the forward fuel tank installed, machine tunnel buildout and framing progressed quickly. Our crew is currently fabricating the windlass and bow-thruster battery box, holding tank, and water tank. Posted on 7 Mar
Construction update: Blue View - Bayliss 78'
Blue View has experienced major progress on the bridge Once the space was glassed in February, the bench seats and brow wall underwent their own rounds of fairing and primer. With the console installed, work begins on the raised teak deck- a unique feature to this build, sure to be a stunner! Posted on 6 Mar
Construction update: Tarheel - Bayliss 62'
The entire flybridge on Tarheel is now in final primer This month, her faux teak drip-molding will be sighted and installed- a defining feature of the cabin which will really bring the exterior appearance together. Posted on 5 Mar
New construction updates - Bayliss 75'
One of the biggest benchmarks checked off in early February- her first sea trial The month of February made things real for Bayliss 75' as this build nears completion. One of the biggest benchmarks was checked off in early February- her first sea trial. Posted on 3 Mar
Construction update: Gypsea - GameBoat 62'
Anproductive January now that her hull is planked, glassed and faired At the end of January, our hull carpentry crew installed Gypsea's main bulkheads, and will soon begin on the buildout of her machine tunnel. Posted on 5 Feb
Construction update: Blue View - Bayliss 78'
Blue View (Bayliss 78') received her aft fuel tank Cockpit cabinetry and work on the mezzanine will be under way soon. On the flybridge, Blue View's console has been fabricated and installed. The bridge bench seats have been faired and are already receiving primer coats. Posted on 4 Feb
Construction update: Bayliss 75'
The interior of Bayliss 75' progressed in leaps and bounds In January, the exterior appearance of Bayliss 75' was inched one step closer to completion with the placement of her tower and hardtop as well as the installation of her teak salon door. Posted on 3 Feb
Blue View (Bayliss 78') gets aft fuel tank
Snuck outside as soon as the New Year began! Blue View (Bayliss 78') snuck outside for her aft fuel tank installation as soon as the New Year began! Posted on 8 Jan
Tarheel (GameBoat 62') cabinetry moving along
Bow deck and cabin are finally in finish primer Tarheel (GameBoat 62') looks different on the outside this month, as her bow deck and cabin are finally in finish primer. Posted on 7 Jan
Bayliss 75' shines in final paint
Emerging from her stay in the paint bay Bayliss 75' emerged from her stay in the paint bay, decked out in Cloud White. Posted on 6 Jan
Raymarine AUS 2018 Aug - Axiom - FooterMarina Exchange FOOTER 1Nanni Diesel 2019 Footer