GameChanger to be christened this week

by John Bayliss 4 Dec 2018 16:32 UTC
GameChanger, feeling the Croatian Sound © Bayliss Boatworks

November was a month full of details for our second GameBoat, the 62' GameChanger.

Upon entering the salon, it's clear that GameChanger's final days in Wanchese are upon us. The salon sofas were fit and installed at November's end, their soft white surface a perfect contrast to the darker, bold veneers in the upper level space. The four-inch teak flooring in the galley received her final top coat this month, adding another layer of shine and protection. The dinette table was installed as well - a solid teak masterpiece, and a brilliant addition to GameChanger's upper level corner space.

On the lower level, soft goods are in - from padded panels to carpet and mattresses. The final details, though small, are adding much to the quality of the interior. The padded headboard is installed in the master stateroom, adding a punch of color to bold teak cabinetry. Wall paneling is drawing attention to stateroom valences, while mattresses are giving shape to bunks in each stateroom.

Moving outside, the cockpit is a hub of activity, as it always is in these final days: the teak has been sanded, while final components like the tackle center, halyard tubes, and rod holders have been installed. Earlier in November, our paint crew placed the finishing details on GameChanger's exterior, with final clear coats on the toe rail, transom, and drip molding. Her boot stripe and bottom paint were applied, too.

GameChanger will be christened on Friday. Look out for final photos, video, and more details!

Read more about GameChanger here

Related Articles

Construction updates: Gypsea Bayliss 62'
The month of June has been an especially busy one for our paint crew With the cabin installed on Gypsea (Bayliss 62'), our crew turned their attention to glassing, fairing, and priming the engine room companionway, aft fuel tank compartment and anchor locker. Posted on 7 Jul
Construction updates: Blue View - Bayliss 78'
Blue View's final teak component, the bulkhead, is now under development Blue View (Bayliss 78') is getting to that point in the process where benchmarks seem to be flying by at a rapid pace. Faired and sanded to perfection by our paint crew, she was blanketed in final primer in late June. Posted on 6 Jul
Construction updates - Bayliss 62'
In a stage of rapid progression With her hull jig assembled, our carpentry crew made quick work of constructing the keel, sheer and chine. Over the course of the last couple of weeks, the crew installed three layers of bottom planking. Posted on 5 Jul
Construction updates - Tarheel Bayliss 62'
Late June was an exciting time at the shop Our very own 62-foot build is getting close to her christening date! Late June was an exciting time at the shop. Department supervisors gathered in the cockpit on Tarheel (Bayliss 62') as we took her out for the first sea trial. Posted on 4 Jul
Construction updates - Gypsea Bayliss 62'
Carlings and cabin go in With her interior walls installed, our crew was able to turn their attention to the installation of her carlings. Shortly after, she checked off another benchmark in the build process- the installation of her cabin. Posted on 7 Jun
Construction updates - Blue View Bayliss 78'
May brought several new teak additions to Blue View On the flybridge, her console is now in final primer. The cabin, bridge, and hull are in the process of being sanded and will soon match the console in final primer. Posted on 5 Jun
Construction updates - Tarheel Bayliss 62'
Emerging from the paint bay looking like a finished boat Tarheel also received her transom paint last month, courtesy of Everett Nautical. Our paint crew will focus on applying her waterline and bottom paint over the next couple of weeks. Posted on 3 Jun
Blank Check (Bayliss 75') delivered
Powered with MTU 16V2000 M9L engines, each with 2,600 horsepower The 75' Blank Check was christened and delivered to her owners in early April. A product of over 68,000 man-hours and nearly 28 months of labor, she will be spending much of her time at southern latitudes. Posted on 11 May
Construction updates - Tarheel Bayliss 62'
Tarheel (Bayliss 62') is now in the home stretch. While the interior carpentry crew continues to work on lower and upper level installs, our metal works department is creating a brand new custom TV lift for the salon. Posted on 9 May
Construction updates - Blue View Bayliss 78'
We hit some serious benchmarks on Blue View's appearance in April. The most dramatic was the installation of her teak toe rail. Work continues on the mezzanine, where the exterior carpentry crew is currently installing five custom stainless steel freezer boxes. Posted on 7 May