GameChanger christening approaches

by Bayliss Boatworks 3 Nov 2018 12:58 UTC
GameChanger, testing the water © Bayliss Boatworks

The month of October made it real for GameChanger: this build is nearly complete. On the interior, we are seeing changes daily. Padded panels are now being fit to each lower level wall, all while other details (towel hangers to cabinetry hardware) are being installed to their final spaces.

GameChanger features our V.C. interior layout option, which allowed the owner a blank slate with which to design the lower level accommodations. A stark contrast to our first GameBoat that utilized the V.1. layout (clean and simple, bunk beds for crew), GameChanger proves our concept: everyone fishes differently, and there are endless options that can be fit into the GameBoat footprint.

On GameChanger's upper level, salon valences have been installed, a final detail that brings such shape to the galley and salon areas. The galley granite is in, a light and easy contrast to the bold teak veneers in the surrounding cabinetry. To finalize the upper level galley cabinetry (and other storage areas), we are cutting customized nesting spaces for kitchen appliances, cups, and bottles of spirits. In November, aside from punch list details, we await completion of the salon sofa, and the final installation of soft goods.

GameChanger will be christened in early December. We'll be so pleased to release her to the world, soon!

Read more about GameChanger here

Related Articles

Blue View (Bayliss 78') gets aft fuel tank
Snuck outside as soon as the New Year began! Blue View (Bayliss 78') snuck outside for her aft fuel tank installation as soon as the New Year began! Posted on 8 Jan
Tarheel (GameBoat 62') cabinetry moving along
Bow deck and cabin are finally in finish primer Tarheel (GameBoat 62') looks different on the outside this month, as her bow deck and cabin are finally in finish primer. Posted on 7 Jan
Bayliss 75' shines in final paint
Emerging from her stay in the paint bay Bayliss 75' emerged from her stay in the paint bay, decked out in Cloud White. Posted on 6 Jan
GameChanger christened in early December
Bayliss Boatworks send their second GameBoat into the world In early December, Bayliss Boatworks sent their second GameBoat into the world with a proper christening. Posted on 5 Jan
Construction update: Gypsea - GameBoat 62'
And just like that, our fourth GameBoat is planked! At November's end, our hull construction crew placed the Whiskey Plank on Gypsea. During November, we managed to complete tunnel construction, install shaft tubes, and begin blocking for the bow thruster. Posted on 12 Dec 2018
Construction update: Tarheel - GameBoat 62'
On Tarheel, our interior crew is making incredible progress On Tarheel, our interior crew is making incredible progress, as buildout in all lower level spaces has begun. The Master stateroom will feature matching bunks on the port and starboard sides, with ample storage above. Posted on 10 Dec 2018
Construction update: Blue View - Bayliss 78'
The interior is beginning to look alive on this incredibly intricate build After the sizable change to the exterior with the addition of the cabin, our crew's attention now turns inward. The lower level buildout and transformation has begun, really demonstrating the size of Blue View - as it houses four staterooms quite easily. Posted on 8 Dec 2018
Construction update: Bayliss 75'
December will be an exciting month for the boat! Teak wainscoting is being installed along the spacious companionway, where the pattern is bold and impressive - a seamless match for the remainder of the teak patterns throughout this build. Posted on 6 Dec 2018
GameChanger to be christened this week
November was a month full of details for our second GameBoat, the 62' GameChanger. Upon entering the salon, it's clear that GameChanger's final days in Wanchese are upon us. The salon sofas were fit and installed at November's end, their soft white surface a perfect contrast to the darker, bold veneers in the upper level space. Posted on 4 Dec 2018
Construction update: Tarheel - GameBoat 62'
Outfitted with her main mechanical components Much like Blue View, now that Tarheel is outfitted with her main mechanical components - our build crew is off to the races. October began with the installation of her two MTU M96L 12V engines Posted on 7 Nov 2018