Tarheel's build crew has jumped quickly into the fabrication of the interior spaces in equal progression from the machine tunnel to the lazarette.

The machine tunnel is framing up quickly, and the faces for both the freshwater and blackwater tanks have been fit and installed. The lazarette progress is most active where the rudder port and shelves are being installed. Just forward, the walls of the aft gyro surround are up, which will soon house one of two Seakeeper 6's.

In the engine room, we are installing the generator and pump room shelving, bilge boxes, and battery boxes. The patterns for the engines will be set up soon, as Tarheel will be receiving her pair of MTU 12V engines (each with 1920hp) the same day that Blue View receives her MTUs in late September.

Click here to see Tarheel's latest general arrangement drawing!

Related Articles

Construction update: Gypsea - GameBoat 62'
And just like that, our fourth GameBoat is planked! At November's end, our hull construction crew placed the Whiskey Plank on Gypsea. During November, we managed to complete tunnel construction, install shaft tubes, and begin blocking for the bow thruster. Posted on 12 Dec
Construction update: Tarheel - GameBoat 62'
On Tarheel, our interior crew is making incredible progress On Tarheel, our interior crew is making incredible progress, as buildout in all lower level spaces has begun. The Master stateroom will feature matching bunks on the port and starboard sides, with ample storage above. Posted on 10 Dec
Construction update: Blue View - Bayliss 78'
The interior is beginning to look alive on this incredibly intricate build After the sizable change to the exterior with the addition of the cabin, our crew's attention now turns inward. The lower level buildout and transformation has begun, really demonstrating the size of Blue View - as it houses four staterooms quite easily. Posted on 8 Dec
Construction update: Bayliss 75'
December will be an exciting month for the boat! Teak wainscoting is being installed along the spacious companionway, where the pattern is bold and impressive - a seamless match for the remainder of the teak patterns throughout this build. Posted on 6 Dec
GameChanger to be christened this week
November was a month full of details for our second GameBoat, the 62' GameChanger. Upon entering the salon, it's clear that GameChanger's final days in Wanchese are upon us. The salon sofas were fit and installed at November's end, their soft white surface a perfect contrast to the darker, bold veneers in the upper level space. Posted on 4 Dec
Construction update: Tarheel - GameBoat 62'
Outfitted with her main mechanical components Much like Blue View, now that Tarheel is outfitted with her main mechanical components - our build crew is off to the races. October began with the installation of her two MTU M96L 12V engines Posted on 7 Nov
Construction update: Gypsea - GameBoat 62' begins
Where the owner's ideal layout is made a reality In October, we began our fourth GameBoat, named Gypsea. At 62', she will feature our V.C. interior layout, where the owner's ideal layout is made a reality within the GameBoat footprint. Posted on 5 Nov
Construction update: Blue View - Bayliss 78'
Blue View's exterior profile is coming to life Prior to the installation of her super structure, Blue View got her pair of MTU 16V engines (each with 2600 horsepower) at October's start, pushing us past a big milestone in her development. Posted on 4 Nov
Construction update: Bayliss 75'
The teak transom, once shiny - is now like a mirror. We know we sound like a broken record when we write about Bayliss 75': teak, teak, teak. But, it's true. Each month our finish crew elevates the bold teak details with dedicated sanding and endless coats of varnish. Posted on 3 Nov
GameChanger christening approaches
The month of October made it real for GameChanger: this build is nearly complete On the interior, we are seeing changes daily. Padded panels are now being fit to each lower level wall, all while other details (towel hangers to cabinetry hardware) are being installed to their final spaces. Posted on 3 Nov