Construction update: GameChanger - GameBoat 62'

by Bayliss Boatworks 6 Jun 2018 09:56 UTC
The drip molding and window lines have been laid on GameChanger © Bayliss Boatworks

GameChanger is a bit different from our first GameBoat, the 60' Mama C, which featured four extra-large bunks with a center companionway.

The GameChanger features our most customizable interior option that seeks to meet our owners' unique fishing needs. GameChanger has a three-stateroom/two-head layout, complete with a custom tackle room.

Over the past month, GameChanger has advanced quickly. Mechanically, our crew has been tackling the chiller and freshwater systems, which have been installed and finalized. The machine tunnel area is complete, as well. In the lower level areas, the heads and shower fixtures are installed, just as sure as the sinks are cut in. Much of the cabinetry in the lower level is installed - both the VIP bunk and nightstands are in place, along with the main cabinetry in the Master stateroom, from the dresser to the hanging lockers.

The cockpit mezzanine has received its refrigerator and freezer boxes, all fabricated in-house. The mezzanine and cockpit are nearly ready for fairing, which means primer will happen before we know it. On the flybridge, the console and bench seat are built out, faired, and in primer. The curtain track on the bridge exterior has been installed, as well.

Next, our electrical team will focus on the electrical layout in the salon, as well as the electronics arrangement on the flybridge console. In June, cabinetry will continue to be fabricated and installed in both the upper and lower levels, while we begin to pattern the window trim and mock up the tackle room.

Read more about GameBoat 62' here

Related Articles

Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids. Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled This past month, we assembled the hull jig for our latest project: Bayliss 64'. Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75' The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun. Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
June was a productive month for our exterior carpentry team June was a productive month for our exterior carpentry team on the walkaround build. Posted on 1 Jul 2023