Blue View - Bayliss 78' construction update: Installation of the main bulkheads finalized

by Bayliss Boatworks 4 May 2018 10:31 UTC
Blue View, from above © Bayliss Boatworks

Now that Blue View (Bayliss 78') is flipped, our crew has finalized the installation of the main bulkheads, and moved on to the buildout of the machine tunnel, forward fuel tank surround, and integral tanks. The cabin is complete and prepared to move out of doors for post-curing this week.

Over the next month, the construction of the salon deck will begin, along with the gyro surround in the lazarette area. Activity in the machine tunnel and pump room will continue, as well. Soon enough, we will begin to layout chases, and finalize the exact placement of all mechanical components!

Read more about Bayliss 78' here

Related Articles

Bayliss Boatworks new construction updates
Sequentis is getting closer to hitting the water! Earlier in March, our mechanical team with the help of Palm Beach Towers installed her custom hardtop. Posted on 2 Apr
Bayliss Boatworks new construction updates
Our first walkaround build is really coming together! Our first walkaround build is really coming together! With full paint complete, Sequentis returned to the main shop's make-ready bay for our exterior carpentry team to prep for tower installation. Posted on 2 Mar
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis January was a heavy month of boat moves for our mechanical team! After being prepped for final paint, Sequentis was shifted over to our paint facility to have her top coat sprayed. Posted on 3 Feb
Bayliss Boatworks new construction updates
Looking forward to utlizing the new boatyard space in the year ahead The Bayliss Boatyard expansion kicked off this past February, and work is winding down as the project timeline comes to a close. Posted on 2 Jan
Bayliss Boatworks new construction updates
Progress on Sequentis is moving right along! Progress on Sequentis is moving right along! Both the mezzanine buildout and cockpit deck installation are now complete. Posted on 2 Dec 2023
Bayliss Boatworks new construction updates
Steady progress is happening on Sequentis Steady progress is happening on Sequentis. Super Build was applied to the bridge and mezzanine, and crews are now sanding these areas in preparation for primer. Posted on 2 Nov 2023
Bayliss Boatworks new construction updates
Our teams had a productive month on Sequentis Our teams had a productive month on Sequentis. With the teak deck installed on the walkaround, our exterior construction crew is continuing progress on the bridge dash, storage compartments, and mezzanine lids. Posted on 2 Oct 2023
Bayliss Boatworks new construction updates
Hull jig for our latest project: Bayliss 64' assembled This past month, we assembled the hull jig for our latest project: Bayliss 64'. Posted on 2 Sep 2023
Bayliss Boatworks new construction updates
July work on Sequentis 60', Max Bet 64' and Bayliss 75' The mezzanine and bridge buildout on Sequentis kept our exterior carpentry crew busy this past month. Storage and seating can be seen on the bridge now, and fabrication on the forward bridge storage compartments has begun. Posted on 2 Aug 2023
Bayliss Boatworks new construction updates
June was a productive month for our exterior carpentry team June was a productive month for our exterior carpentry team on the walkaround build. Posted on 1 Jul 2023