Jarrett Bay Boatworks new construction updates

by Jarrett Bay Boatworks 27 Apr 18:25 UTC
Jarrett Bay
 
FacebookInstagramYouTubeLinkedIn
Jarrett Bay Insider

NEW Episode!
Flipping the New 90 footer!

Episode 22

Witness a transformative milestone in our construction journey as we roll over the 90 ft. Hull 68, revealing the meticulous planning and execution behind the scenes. Join us as we capture the excitement and anticipation of this significant moment.

Watch the Latest Episode

New Construction Updates

Hull #68: 90' Sportfisherman

As the crew turns the hull right side up, a new phase of construction begins for our 90ft vessel. Workstation access has been set up, and focus has shifted to three primary zones: down forward floor spaces, lazarette, and the engine room. View Construction Gallery >
 

Hull #64: 68' Sportfisherman

Work progresses rapidly across key areas: bridge, mezzanine, engine room, salon, and down forward. The finish shop bustles with activity, preparing intricate components like the wainscoting panel (pictured). Meanwhile, precision installations, like the toe rail, mark significant milestones.
View Construction Gallery >
 
 
Share the Flare
Share Share
Tweet Tweet
Share Share
Forward Forward
 
Copyright © 2024 Safe Harbor Jarrett Bay, All rights reserved.
 

Related Articles

Jarrett Bay Boatworks new construction updates
The fairing process is in full swing on Hull #68 On the exterior of the hull, the fairing process is in full swing as our paint crew longboards the sides. Pretty soon they'll pull a tight skim of putty into the low spots and take it to the next level. Posted on 26 Feb
Jarrett Bay Insider, episode 21
A detailed look at achieving perfection Enjoy a deep dive into the craftsmanship of a truly custom Jarrett Bay interior. Plus, catch a glimpse of what it takes to exact a flawless finish on the 90-foot Hull 68! Posted on 24 Feb
Jarrett Bay Boatworks new construction updates
Progress continues throughout Hull #68, Hull #64 On Hull #68: 90' Sportfisherman all exterior details were brought to completion including the chine spray rail and bow thruster opening and deflector. Posted on 29 Jan
Jarrett Bay Insider, episode 20
The art and history of custom mezzanine design Truly custom tricks of the trade! Q&A with Finish Carpenter Foreman, Josh Fulcher, Dive into the history of custom mezzanine design. Posted on 27 Jan
Jarrett Bay Insider, episode 19
What goes up, starts upside down Tag along as we go in-depth into the custom construction process with the new Jarrett Bay 90 - built upside down on a massive, precisely leveled jig. Posted on 9 Dec 2023
Jarrett Bay Boatworks new construction updates
Sanding and dressing the ribbands, stringers, and hull sides While a team works on the chine spray rail on the exterior of the hull, our crews have begun the process of sanding and dressing the ribbands, stringers, and hull sides in preparation for tabbing and glass work. Posted on 8 Dec 2023
Jarrett Bay Boatworks Hull 65 Rebelette delivered
Watch Jarrett Bay Insider, Episode 18 Lift Films loaded a few memory cards full of photos and footage aboard the all-new 64' Jarrett Bay. Posted on 11 Nov 2023
Jarrett Bay Boatworks new construction updates
With planking complete on Hull #68, our crews began cutting holes into the hull With planking complete our crews began cutting holes into the hull. Bow thruster and sea chest openings are cut along with recesses for the Dyna-Plates. We complete these items before the bottom glass to help eliminate any tabbing buildup. Posted on 9 Nov 2023
Jarrett Bay Boatworks new construction updates
Born to fish, built to win The side planking is complete with the exception of the last bow plank which was chosen to be the whisky plank. The three layers of bottom planking are in different stages of completion. Posted on 12 Sep 2023
Jarrett Bay Boatworks new construction updates
Progress on Hull #68, Hull #65, Hull #64 With the transom planking completed, our crews are now working from aft forward on the first layer of hull side planking along with planking the bottom and prop tunnels. Posted on 27 Jul 2023